RDF Combined Heat and Power Plant Oostende: First RDF-Fire on 04.05.09 as scheduled

After a planning and erection period of two years the milestone "First RDF Fire" was reached as scheduled.

The next step is the commissioning of the turbine in June. The pictures show the first RDF fire and the total view of the plant.

The plant has a firing capacity of 70 MW and produces 80 t/h steam with 40 bar and 400 °C.

The steam will mainly be used in a turbine type MARC 6 from MAN.

 