First Synchronisation of the new fat combustion unit in Oostende

Fat combustion unit

After only four months of construction time the first of two GenSets of the power plant in Oostende was synchronised on December 12th.

The power plant has an electrical power of 2 x 8.3 MW. The plant will be operated with refined animal fat. The GensSets are heavy fuel oil engines with an electrical power of 8.3 MW each.